PID 117642

PROJECT INFO SHEET

This project is to replace the superstructure of Old Stage Road bridge.

PROJECT LOCATION

The Old Stage Road bridge is located 3/4 mile north of Mt. Holly Road in Spring Valley Township, passing over Bear Run.

STATUS

The Old Stage Road bridge is currently rated at a 3 and has been closed since 2015.  

This project consists of replacement of the superstructure with a galvanized steel plate girder with a composite concrete deck (not fracture critical) with minimal approach work.

BACKGROUND

The 140 foot long Old Stage Road bridge was built in 2000 but closed in 2015 due to its poor condition.  It was built as a single span weathering steel truss (fracture critical) bridge.

The County Engineer holds paramount the safety, health, and welfare of the public.  

  • The emergency response time by fire and emergency services is greatly affected by this closure.
  • The school routes for buses is greatly affected by this closure.
  • The existing bridge superstructure is failing and needs removed and replaced.

SUCCESSFUL FUNDING TIMELINE

  • Construction cost estimate is $1.545 million
  • 100% funding for engineering and construction has been obtained through the County Engineer Bridge Formula Program

        Bridge Formula Program Application PDF

        Bridge Formula Program Acceptance Letter PDF

        Old Stage Bridge 30% Plans

SCHEDULE

Authorized Design Consultant                   10/01/2022

Stage 2 Plans Submitted                           02/01/2024

Environmental Document Approved          03/18/2024

Stage 2 Plans Complete                            03/01/2024

R/W Authorized                                          03/04/2024

R/W Acquisition Complete                          01/10/2025

Final Tracings Approved                             01/10/2025

Sale                                                             04/18/2025

Award                                                          05/19/2025

Estimated Begin Construction                     07/18/2025

Estimated End Construction                        11/21/2025